

Deposit Price (5million) Feedstock: Coconut Husk Focus: Small-scale demonstration for Coconut Husk-to-diesel & Coconut Husk-to-electricity Duration: Installation ~60 days, training & commissioning ~7 days Engineer: On-site for full installation and commissioning

Turns organic waste (like food waste, biomass, or some landfill organics) into biochar and syngas.
Heat the waste without oxygen → it carbonizes into: Biochar (solid, can be used for soil improvement or energy) Syngas (can be used to heat the reactor or generate electricity)
6–8 tons of biomass → ~2 tons biochar, ~2–3 tons gas for heating/electricity, small amount of liquid, and some ash.
Feedstock procurement for per ton of coconut waste - 40 tph
Machines take in raw material continuously, process it with heat, recycle gas for energy, and output products continuously, so you don't have to stop and restart each time.
limited only by maintenance, feedstock supply, or cleaning needs.



Wiring of all motors, pumps, and control panels. Connection to on-site transformer or grid.
Installation of sensors: temperature, pressure, flow meters, level sensors. Control system setup (PLC or SCADA interface if available).
Wiring and grounding of distillation unit. Functional testing of motors, pumps, fans, and alarms.
Installation of water cooling piping and drainage connections
Installation of gas exhaust ducts for Carbonization Machine (if using syngas internally)
Leak testing and pressure testing of pipelines. Installation of valves, fittings, and expansion joints

Dry-run of equipment without feedstock. Functional testing of motors, pumps, conveyors, and distillation skid.
Calibration of sensors, meters, and control systems.
Trial runs with small quantities of feedstock. Adjustment of temperature, pressure, and feed rates for optimal operation.
Safety checks: emergency stops, fire suppression, alarms
Land clearing & debris removal. Excavation & leveling for foundations and storage areas. Soil compaction and stabilization.
Temporary access roads for trucks & cranes. Drainage planning to prevent flooding. Dust control measures (water spraying or covering).

Reinforced concrete foundations for Plants. Anchor points for heavy machinery.
Chemical/oil-resistant flooring in feedstock/product handling zones.
Platforms for feedstock loading and finished product collection. Safety barriers and handrails around equipment zones.
Minor steel structures for support if required.
Designated feedstock storage areas (Husk). Product storage: pyrolysis oil tanks, biochar bags, syngas handling (if used for energy). Chemical storage racks (lubricants, solvents, additives). Covered areas for trucks and material handling. Loading/unloading ramps and platforms.
Small on-site office or control room. Worker shelters and restroom facilities. Tool storage and maintenance workshop. Fire safety infrastructure (hydrants, hoses). Emergency evacuation paths.
Minor unforeseen costs during installation. Additional safety equipment or spare parts. Minor modifications to foundations, piping, or electrical connections. Consumables (wires, bolts, welding rods, lubricants).
6 months
on $5.7 M CAPEX
Dominican Republic Coconut Pilot Program